Alabama tightens data-center rules but keeps default approval


Alabama Power must disclose more about electricity contracts, while a 90-day exception still allows large projects to gain approval without a public vote.
Alabama’s utility regulator approved rules on 6 October requiring fuller disclosure of future data-center electricity contracts and public votes on projects above 150 megawatts, a unit of electrical power, while allowing approval without a vote after 90 days. The commission has since issued its final order, and Alabama Power’s filing sets 23 November as the effective date, Inside Climate News reported on 23 October.
Previously, data centers—facilities housing large groups of computer servers—followed the approval process for other large industrial sites. No separate commission vote was required, and contracts gained approval unless the commission acted within 10 days. The new rules followed an Alabama law passed in 2026 requiring stronger disclosures.
The final order follows the Alabama Public Service Commission’s 3–0 vote approving the framework. It requires Alabama Power to give complete contracts, without information blacked out, to the commission and the Alabama Attorney General’s Office. The attorney general’s office serves as the state’s advocate for utility customers.
The agencies have 90 days to check whether each contract serves the public interest and requires the data-center customer to cover all electricity-service costs, including new infrastructure and fuel. Contracts must include financial details showing that the facility pays the costs it creates.
The public must receive a copy with some information blacked out, but it must identify the electricity customer and its parent company, the project’s location and its maximum electricity capacity. Commission president Cynthia Lee Almond said the earlier public filings concealed much of the important information.
Monika Gerhart said the final rule delivered much of the transparency her group sought, but allowed information used to calculate effects on electricity bills to remain confidential. She said outsiders could not check whether households and businesses were paying data-center costs or whether options without fuel bills, such as solar power, received fair consideration. Her criticism concerns the ability to check those calculations, rather than an established finding that costs have been shifted.
Alabama Power said it would continue requiring large data-center customers to pay the full cost of serving their electricity needs so those costs are not shifted to existing customers. The company said Alabama law requires that standard and that the commission approves contracts meeting it while providing benefits to other customers.
Jaclyn Brass, an attorney in the Southern Environmental Law Center’s Alabama office, called the process an improvement but said stronger protections were needed to prevent customers from paying for data-center expansion.
During the framework’s approval, Commissioner Chris Beeker III proposed default approval to encourage timely decisions. Almond supported public votes because of data centers’ size, electricity use and public concern. The final order retains the exception: contracts are considered approved if the commission takes no action within 90 days.
A commission spokesman said the agency considered public comments and still intends to vote on every contract within the review period. He said default approval does not change the public-interest standards governing those decisions. Projects approved without a vote must be announced at the next commission meeting.
Daniel Tait, executive director of the clean-energy advocacy group Energy Alabama, welcomed required votes but remained disappointed that inaction can count as approval and that review details are not public. The Southern Environmental Law Center also opposed the exception and noted that the rules do not require public hearings or other opportunities to comment on individual proposals.
The original order directed Alabama Power to prepare a compliant rate schedule within 10 days, with changes taking effect no sooner than 30 days afterward. The utility, which said it was committed to following the requirements, filed its tariff—the document setting out the electricity-service terms—on 21 October. That filing sets 23 November for the new disclosure and review process to begin.
The Linux desktop project's restriction reaches beyond code to the wording submitted for review. GNOME projects also restrict generated contributions, but their rules differ.
2 min

The cooperation framework focuses on access to technology, women’s and girls’ role in shaping it, and protection from digital risks.
2 min

Commissioner Carly Kind says privacy obligations may fall on the software provider rather than a retailer that collects no personal information in connection with the devices.
2 min