NASA completes Artemis III boosters and installs four engines


NASA plans to join the rocket’s central stage to the boosters for a propellant-loading test and crew emergency-exit rehearsal, without Orion or the upper adapters.
NASA has completed both five-segment solid rocket booster stacks for Artemis III and installed all four RS-25 engines on the core stage, the rocket’s central stage, NASASpaceflight reported on 14 October. Joining the stage to the boosters remains ahead, before a planned propellant-loading test and crew rehearsal at Kennedy Space Center.
Stacking began with the bottom booster segments on Mobile Launcher 1 on 13 July, followed by the center segments on 20 August. Engineers finished the stacks on 30 September by adding the forward assemblies, including the nose cones, inside the Vehicle Assembly Building’s High Bay 3.
Artemis III remains targeted for no earlier than June 2027. Rather than travel to the Moon, Orion and its four-person crew are planned to stay in low Earth orbit and demonstrate docking and other operations with lunar modules from SpaceX and Blue Origin. Those tests are intended to reduce risks before the first crewed lunar landing attempt on Artemis IV, currently planned for 2028.
Engineers must next install the systems tunnel, a channel along the core stage that carries wiring for single-use connections that detach at liftoff. The 14 October report said the stage would then be joined to the boosters in the coming weeks. This partial configuration, called the short stack, will leave off Orion, the upper-stage adapters and the spacer.

During the pad visit, the crew will conduct its first full launch-day rehearsal there. The astronauts will put on their suits, travel from the crew quarters to the pad, ascend the mobile launcher and walk through the emergency-exit route they would use if something went wrong during the countdown.
NASASpaceflight’s 6 October report also described production of a connecting ring for the core stage associated with Artemis VI. NASA’s stated plan is to switch to commercial vehicles for crew flights to lunar orbit after Artemis V. The report described the ring work as consistent with starting time-consuming manufacturing as a contingency if commercial alternatives are not ready. Whether the hardware will become a completed stage remains unclear; the finished ring would be welded to Core Stage 6’s engine section if assembly proceeds.
At Kennedy Space Center, engineers connected Orion’s crew module to its European Service Module through umbilicals, connections that carry power between the modules. NASASpaceflight reported on 6 October that the crew module had received power through those connections for the first time, confirming the electrical connection before further testing of the modules together.
At Marshall Space Flight Center, both connecting rings have now been welded onto the Artemis III spacer, completing its main structure. Engineers are checking its dimensions before planned shipment to Kennedy in early 2027.
NASA is converting stored structural test articles—hardware built for structural testing—of the Orion Stage Adapter and Launch Vehicle Stage Adapter into flight hardware for Artemis III. These components connect sections of the rocket. Using them preserves the production flight units for Artemis IV, but their years in storage require additional preparation.
Exterior painting of the Orion Stage Adapter is complete, with cable and bracket installation next. Its preparation also includes insulation before installation on the rocket in 2027. Corrosion removal on the Launch Vehicle Stage Adapter is nearly finished; checks that do not damage the hardware are scheduled for autumn 2026, followed by protective coating, primer, paint and thermal-protection foam. The adapters are scheduled to join the short stack after the tanking test.
Orangetown and Clarkstown have different six-month restrictions. DataBank’s expansion is exempt from the town pause but faces a disputed state decision and further environmental review.
3 min

The mapping portal warns of prosecution for downloads without written approval. Experts fear the requirements will hinder tracking of illegal forest clearing.
2 min

The five-member team competed in Hanoi, Vietnam, from September 25 to October 5, 2026.
2 min