Rooppur Unit 1 supplies Bangladesh’s first nuclear electricity


The plant connected to the national grid on 17 November 2026, for an initial test. Further trials and regulatory approval must precede regular commercial supply.
Rooppur Unit 1 supplied Bangladesh’s national grid with nuclear-generated electricity for the first time at 15:16 Bangladesh time (13:16 Yerevan time) on 17 November 2026. The connection was a test, not the start of regular commercial service.
The unit reached 350 megawatts 29 minutes after connection and later peaked at 375 megawatts, below its rated capacity of 1,200 megawatts. Bangladesh’s Nuclear Power Plant Company Bangladesh Limited (NPCBL), which operates the plant, had planned an 8–10 hour supply to monitor stability and test how the turbine, generator and grid worked together.
The first run lasted about eight and a half hours and ended at 23:50 Bangladesh time (21:50 Yerevan time). NPCBL managing director Zahedul Hasan said the disconnection was temporary, to prepare for further technical tests, Ajker Bangladesh said on 19 November.
NPCBL had planned another four-to-six-hour connection after a break of about 28 hours for technical and operational tests. The company said the Bangladesh Atomic Energy Regulatory Authority must approve the next phase of trial operation. Project officials said output would then rise in stages to test the reactor, turbine, generator and automatic controls.
Hasan said NPCBL was working toward supplying approximately 1,150 MW by February or March 2027 and expected that output to substantially ease Bangladesh’s summer electricity shortfall. NPCBL said regular commercial supply at full capacity would follow successful technical tests and a 10-month trial operation.

The company said on 18 November 2026, that hot and cold tests were under way at Unit 1 in Mersin after Turkey’s nuclear regulator authorized them. The checks precede a decision on loading real fuel.
The Bangladesh Atomic Energy Commission is implementing the project under the country’s science and technology ministry, while Russian contractor Atomstroyexport is building the two units. Russia’s Rosatom signed an agreement for the reactors in February 2011 at Rooppur, about 160 kilometres from Dhaka. The initial project contract was signed in December 2015, construction of Unit 1 began in November 2017, and the first nuclear fuel reached the site in October 2023, World Nuclear News said on 17 November.
The unit received its operating license on 16 April 2026, completed fuel loading in May and reached criticality—a self-sustaining nuclear reaction—on 11 October.
2 min

The partners signed an exclusive memorandum on 19 November 2026, to develop a demonstration ship that would use a nuclear reactor for propulsion while carrying liquefied natural gas across the Atlantic.
3 min

The chipmaker plans to become the first customer outside the automotive industry to test the humanoid robot, with work at its facilities set to begin in early 2027.
2 min