Black Hills plans $1.8 billion for proposed Google data center

The Cheyenne, Wyoming, project would combine utility grid power with third-party resources. Black Hills says Google must cover the full cost of electricity supply.

The Cheyenne, Wyoming, project would combine utility grid power with third-party resources. Black Hills says Google must cover the full cost of electricity supply.
Black Hills Corp said on October 6, 2026, that it had signed agreements to power Google's proposed data center in Cheyenne, Wyoming. The South Dakota-based utility plans to spend $1.8 billion on new electricity generation capacity from 2027 through 2029, according to Reuters reporting published by CNA.
The deal comes as technology companies seek electricity for power-hungry data centers. For the proposed Cheyenne site, Black Hills would both supply power from the grid and manage resources provided by third parties.
Black Hills distinguishes the generation capacity it plans to build from the electricity it would supply through the grid and the third-party resources it would manage. A megawatt (MW) measures power; a gigawatt (GW) is 1,000 MW.
| Component | Amount | Black Hills' role |
|---|---|---|
| New generation | 564 MW | Build new generation capacity for the project. |
| Grid supply | Up to 590 MW | Supply electricity mostly from a new gas plant at its Cheyenne Prairie Generating Station. |
| Third-party resources | About 2.1 GW | Manage resources in Wyoming through a private microgrid, a local electricity network. |
Black Hills expects the project to draw on a total resource mix of 2.7 GW, including reserve margins—extra capacity above expected demand. That figure describes the resources available, including reserves, rather than the data center's peak electricity demand.
Black Hills says the agreement requires Google to cover the full cost of supplying electricity to the data center. The utility says this provision prevents those expenses from being passed on to other customers.
The utility expects the project to add about $150 million to its net income by 2030. Black Hills schedules the first power deliveries for late 2027 and expects the data center's electricity demand to reach its peak in 2030.

Google plans to build the facility with Tallgrass Energy, Black Hills Energy, American Electric Power and Related Digital, bringing the company’s data-center construction plans to a new state.