Lake Sevan wastewater plan awaits funding and final approval

The proposed $101.7 million first phase would upgrade three treatment plants and extend sewerage to about 74,000 more residents.

The proposed $101.7 million first phase would upgrade three treatment plants and extend sewerage to about 74,000 more residents.
A proposed $101.7 million wastewater upgrade for the Lake Sevan basin remains without secured financing or final approval, according to EVN Report’s feature “Lake Sevan’s Peril: Can a $270 Million Plan Turn the Tide?”, the sole source for this story. The first phase would expand sewerage and add treatment intended to reduce nutrient pollution entering the lake.
The Public Investment Committee, chaired by Prime Minister Nikol Pashinyan, endorsed the project in July 2026. That endorsement was not final financing approval: the Water Committee’s spokesperson told EVN Report that financing discussions continue, no allocation has been made and the program should not be considered finally approved.
EVN Report says wastewater treatment in the basin has been mechanical since 2013, with no biological treatment before discharge into the lake. Mechanical treatment screens wastewater and removes grit and grease. The proposed upgrades at the existing Gavar, Martuni and Vardenis plants would add biological treatment, intended to reduce phosphorus and nitrogen reaching Sevan and help curb algal blooms.
According to the Asian Development Bank’s feasibility study, as described by EVN Report, more than 70% of urban wastewater in the basin is neither collected nor treated. The study identifies phosphorus pollution as the main driver of accelerating eutrophication—the enrichment of water with nutrients that encourages algal blooms. Reduced nutrient inflows are an expected effect of the proposed work, not an achieved result or a guarantee of lake restoration.
EVN Report says the Asian Development Bank and Armenia’s Water Committee, the government body responsible for managing water resources, agreed on a three-phase program totaling $269.7 million. The smaller first phase would build and restore sewer lines and pumping stations alongside the three plant upgrades.
| Measure | Amount or residents served |
|---|---|
| Full three-phase program | $269.7 million |
| Proposed first phase | $101.7 million (39.65 billion AMD) |
| Residents already connected | About 30,000 |
| Residents newly connected under Phase 1 | About 74,000 |
| Total residents served after Phase 1 | About 104,000 |
The feasibility study, as reported by EVN Report, identifies three high risks: delays in completing household connections, fewer connections than expected reducing the plants’ operating efficiency, and uncertainty over who would operate the plants after the upgrades. These risks concern whether the expanded sewerage network and upgraded plants would function as intended.
EVN Report gives an estimated five-year duration for Phase 1, with expected completion in early 2032; details of Phases 2 and 3 are not yet being discussed. The Water Committee’s spokesperson said preliminary calculations envisage partial government co-financing in the 2027 budget, with the remainder expected through an Asian Development Bank grant. Those financing arrangements remain under discussion, rather than committed funding.

The infrared image shows young stars alongside cavities and disturbed gas. ESA explains how stellar outflows, winds and light reshape the cloud around them.
3 min

A model of rock beneath the Moon’s far side favors a long-lived field over an impact’s brief magnetic pulse, but the lunar dynamo debate remains open.
3 min

The assessment considered vaccination coverage, prevention of transmission around birth and signs of infection among vaccinated groups.
2 min