New South Wales passes Mount Pleasant coal mine expansion law

The measure raises MACH Energy’s annual extraction limit from 12.5 million to 16.5 million tonnes through 2032, after a court invalidated a larger expansion. A jobs guarantee must be signed before the new consent takes effect.
In this article
New South Wales lawmakers have passed special legislation allowing MACH Energy’s Mount Pleasant thermal coal mine near Muswellbrook to extract more coal, subject to a jobs guarantee. Labor and the Coalition secured passage at 01:36 local time on 21 November (18:36 Yerevan time on 20 November).
The vote followed an October High Court ruling that invalidated approval for a larger expansion to 21 million tonnes a year through 2048. By 3–2, the court found that the state’s Independent Planning Commission had failed to properly consider conditions to minimize greenhouse gas emissions from burning the exported coal overseas.
Jobs guarantee and emissions conditions
The guarantee covers more than 720 mine workers. The government said it must protect all permanent workers and be signed before the new consent takes effect. MACH Energy must report permanent workforce levels quarterly, with significant fines for reductions made without ministerial approval; the resources minister can order mining to stop as a last resort if the company breaches the guarantee. Mine data supplied for the agreement is subject to an independent audit.
The government said up to 400 jobs were at risk without intervention. The guarantee covers the wider workforce, not just those jobs. ABC said MACH Energy had projected 575 personnel under a separate permit, about 125 fewer than under the larger expansion; the company did not answer the outlet’s questions about the jobs figure.
Premier Chris Minns said the intervention would protect jobs and warned that a mine closure would raise Muswellbrook’s unemployment rate by 5%. The Mining and Energy Union welcomed the legislation.
The government said the temporary consent would include emissions conditions limiting coal exports to countries with emissions-reduction policies in line with the Paris Agreement. Greens climate spokesperson Sue Higginson said the bill turned away from the NSW Net Zero Commission’s advice that further coal mine expansions are incompatible with the state’s legislated emissions-reduction targets.
Ministerial power draws legal concerns
An amended provision lets the resources minister override state laws as they apply to the development. It cannot be used to change the production limit or prevent changes from being investigated by the Independent Commission Against Corruption.
Parliament’s Legislation Review Committee said the bill would undermine pending court proceedings and procedural fairness by removing avenues for legal challenge. Barrister Geoffrey Watson warned that the ministerial power posed a serious corruption risk, while the Law Society of NSW raised rule-of-law concerns. Resources Minister Courtney Houssos said the government had amended the provision after considering concerns and recognized the importance of safeguards and accountability.
Higginson also alleged that Minns was motivated by the threat One Nation posed to Labor seats in the Hunter ahead of the March 2027 state election. The government’s stated reason was to protect jobs.
The expansion returns to court
The Denman Aberdeen Muswellbrook Scone Healthy Environment Group, a residents’ group, successfully challenged the commission’s 2022 expansion approval in the NSW Court of Appeal. MACH Energy appealed to the High Court, which dismissed its appeal. A separate change to the original permit in August 2026 had extended it to 2032 and raised the annual limit from 10.5 million tonnes.
The NSW Land and Environment Court is expected to hear the matter in December 2026. It must decide whether to suspend the original expansion consent in whole or in part and set terms for compliance that could validate it.
The government said the temporary authorization allows production of up to 16.5 million tonnes a year until 2032 or until a new consent is granted.
Follow AveNews
Earlier in Politics
RightsFrench court sentences 3 officers to 5 years over Michel Zecler beating
The court suspended 3 years of Aurélien Lapersonne’s term, 3 and a half of Philippe Tondeux’s and 4 of Pierre Plantier’s; Plantier is to serve his remaining year under electronic monitoring. It found the officers guilty of violence and falsifying a public document, with racism an aggravating circumstance.
2 min
ConflictRussian strike kills 2 in Kryvyi Rih, injures 42, officials say
Two ballistic missiles hit a restaurant parking lot in the city center late on 20 November, Oleksandr Vilkul said. He said drones struck again as crews responded.
2 min
ConflictIsraeli settlers carry out over 400 harvest attacks, humanitarian team says
A humanitarian group says the attacks caused casualties or property damage in the occupied West Bank and urges Israel to protect farmers as the olive harvest window closes.
2 min
Sources
Show all 5 sourcesShow fewer
Guardian WorldNSW passes Mount Pleasant coalmine law as Greens claim change an attempt to head off One Nation (opens in a new tab)
- nsw.gov.auLegislation to save 400 Hunter jobs at Mt Pleasant to be introduced today | NSW Government (opens in a new tab)
- edo.org.auMount Pleasant Bill introduced to NSW Parliament - Environmental Defenders Office (opens in a new tab)
- abc.net.auNSW government proposal to allow Mount Pleasant mine to continue expanding - ABC News (opens in a new tab)
- abc.net.auHigh Court rules in favour of climate group in Hunter Valley coalmine case - ABC News (opens in a new tab)