Review finds 294 Russian federal building projects worth $115.9 billion delayed


A review of federal records found the projects behind schedule since Russia’s full-scale invasion of Ukraine; the Construction Ministry has recommended deferring some unstarted work to fund projects already underway.
A review of Russian government records found 294 federally backed construction projects behind schedule since Russia’s full-scale invasion of Ukraine, with a stated value of 9.5 trillion rubles ($115.9 billion).
The Moscow Times’ Russian service examined the capital construction project register and federal agencies’ program records. Its review found that, of 1,238 projects, 402 were complete, 160 were on schedule and work had not begun on 382. The government had not formally announced that any delayed projects were suspended or canceled.
The review did not specify its data cutoff, the deadline used to identify a delay, the basis for project costs or the exchange rate used for dollar conversions.
Officials most often cited a lack of funding when moving deadlines and less often a shortage of necessary equipment. The review counted 81 extensions in the partial 2026 tally; some projects had their deadlines extended more than once.
| Year | Extensions |
|---|---|
| 2021 | 15 |
| 2022 | 24 |
| 2023 | 26 |
| 2024 | 59 |
| 2025 | 86 |
| 2026, partial count | 81 |

Transport had the most delayed projects: 128 worth more than 3.4 trillion rubles ($41.5 billion). Health care followed, with 43 hospitals and specialist clinics valued at 438.5 billion rubles ($5.35 billion). Utilities ranked third, with 11 delayed projects.
The Northern Latitudinal Railway, intended to connect the Yamal-Nenets region with the Urals rail network, is scheduled to open in 2031. In Krasnoyarsk, the opening of a light rail line moved from 2026 to 2029 after its projected cost rose. A city official said residents were counting on the line to cross the city without sitting in traffic.
In the Stavropol region, a cancer treatment facility is behind schedule, and patients have reported waiting up to six weeks for appointments. A water-supply project intended to address shortages in eastern Crimea was originally due for completion in 2020; its opening was delayed by 9 years.
The latest schedule for the Ust-Luga gas complex calls for its gas processing and petrochemical plants to open in 2026 or 2027, and its liquefied natural gas plant in 2027 or 2028.
In June 2026, Russia’s Construction Ministry recommended putting off projects that had not broken ground so funding could go toward finishing those already underway. The unstarted projects included 47 education facilities and 34 medical facilities.
Most unstarted projects had no listed price. Those with published estimates were together worth more than 1 trillion rubles ($12.2 billion).
The consulting company aims to reach the target through voluntary departures from its Lisbon teams by January 2027, then assess whether further restructuring is needed.
2 min

UniCredit has committed to keeping the German bank’s headquarters in Frankfurt and retaining its stock-market listing after reaching an agreement in principle with the German government.
2 min

The Alibaba affiliate made around 10.6 billion yuan in the quarter ended 30 June, according to a calculation from Alibaba’s earnings report.
1 min