Spain’s cabinet approves renewable power rules for data centers

New large facilities must cover 80% of their annual electricity use with qualifying renewables. Separately, ministers approved a €17.14 billion (about $18.8 billion) transmission plan intended to accommodate 47.4 GW of new demand through 2030.
In this article
Spain’s Council of Ministers approved the data-center decree on 20 November, setting energy, environmental, resilience and digital-sovereignty requirements. The main rules apply to new centers and expansions with at least 10 megawatts (MW) of grid access; an August draft had proposed a 1 MW threshold.
The government says the rules address a risk that data centers’ relatively steady demand could require more gas-fired generation and raise electricity prices. It also wants important public information systems to remain under European legal and jurisdictional protections.
Renewable power and grid flexibility
Qualifying centers must show that the required annual share of electricity comes from on-site renewable generation or long-term purchase agreements with new renewable facilities, pv magazine said. Separately, the government says centers must match 80% of their consumption with renewable generation hour by hour until renewables exceed 90% of national electricity generation.
The renewable generation generally must have entered the electricity system no more than 36 months before the center starts operating, with exceptions for solar installations, certain biomass plants and upgrades to existing facilities. Self-generation, storage and supply contracts lasting more than six years count in the calculation.
For five years after approval, centers can instead join the Automatic Power Reduction System and accept priority disconnection. They must then demonstrate 60% additional renewable consumption during peak hours through 31 December 2028, and 70% during peak and intermediate hours thereafter until the five-year period ends.
Compliance is tied to grid access, and centers may have to reduce demand or disconnect loads during congestion or system stress. Certain shortfalls can trigger automatic payments proportional to the deviation, as well as sanctions including suspension of access and connection rights for up to three years.
Efficiency, reporting and projects in progress
The decree also sets energy and water efficiency requirements. Power usage effectiveness measures a facility’s total energy use against the energy used by its computing equipment; water usage effectiveness measures water use against computing energy use. Transitional maximums are 1.25 for the dimensionless power-use ratio and 0.1 liters per kWh for water use. Later rules will use the highest European water-efficiency classification and an energy-efficiency method that takes account of Spain’s climate zones.
Projects already being processed have six months to adapt and demonstrate compliance, or three months if they are awaiting a grid-access competition. They can instead give up access and connection rights without forfeiting the associated guarantees.
Some obligations reach smaller facilities. Centers above 500 kilowatts must submit efficiency and sustainability data to Spain’s ecological transition ministry for annual publication; those above 1 MW must also report on compliance with the latest European data-center energy-efficiency code. Rules for sensitive public information systems apply regardless of center size, including requirements on where sensitive data is held and controls on access from outside the European area.
A separate plan for the transmission network
Separately, the cabinet approved a €17.14 billion (about $18.8 billion) transmission plan through 2030 intended to accommodate 47.4 GW of new electricity demand.
The binding infrastructure plan calls for 6,707 km of new transmission lines, capacity upgrades on 8,164 km of existing lines and 193 substations. Red Eléctrica de España, the system’s sole transmission operator, will carry it out.
| Use | Capacity |
|---|---|
| Industry | 14.9 GW |
| Renewable hydrogen and derivatives | 12.4 GW |
| Data centers | 9.3 GW |
| Housing and territorial development | 6 GW |
The 9.3 GW data-center allocation covers projects already granted transmission access or included in a 2024 planning modification. Red Eléctrica calculates that the planned measures will save the electricity system more than €3.59 billion a year; those savings are a projection.
Government estimate and industry response
Sara Aagesen, Spain’s third deputy prime minister and ecological transition minister, said data-center projects had secured 15 GW of grid-access capacity, including 6 GW on the transmission network and 9 GW on distribution networks, with another 20 GW of capacity awaiting grid access. Spain’s 2024 AI Strategy forecast less than 4 GW of data-center electricity demand by 2030.
Aagesen said one scenario without the decree would add €5 billion a year to electricity costs and leave industrial users paying 25% more for electricity. SpainDC, a data-center industry association, has asked the government to explain the estimate’s origin and method.
SpainDC says operators face an impossible choice between renewable matching requirements and priority disconnections that conflict with continuous operation. It plans to challenge the decree in court and seek a precautionary suspension. Multinacionales con España, an association of foreign-owned companies, has called for an economic impact assessment and continued dialogue, saying the matching rules may create technical and economic difficulties.
Follow AveNews
Earlier in Technology
SoftwareFBI investigates apparent intrusion into US crime database
The system connects law enforcement agencies across the country for warrant and background checks; the FBI had no comment as of Friday night, NBC News reported.
2 min
SecurityStates agree to continue autonomous weapons talks through 2028
The Geneva conference left open whether future rules will be binding after the US, Russia and Israel opposed that approach.
2 min
RoboticsUS drug regulator clears Hugo robot for general surgery, Medtronic says
The company announced the expanded US clearance on 17 November 2026, allowing the system to assist with abdominal operations beyond its earlier urology uses.
3 min
Sources
Show all 7 sourcesShow fewer
- miteco.gob.esEl Gobierno aprueba el Real Decreto para la sostenibilidad energética, medioambiental y de resiliencia y soberanía digital de los centros de datos (opens in a new tab)
pv magazineSpain approves new data center rules requiring 80% renewable electricity (opens in a new tab)
- miteco.gob.esEl Gobierno aprueba la Planificación Eléctrica en el horizonte 2030, diseñada para atender las nuevas demandas propiciadas por la transición energética (opens in a new tab)
- europapress.esEl Gobierno aprueba el 'megaplan' de 17.142 millones en redes eléctricas para impulsar 47 GW de nueva demanda (opens in a new tab)
- elespanol.comEl PP derogará el decreto de centros de datos y la patronal del sector recurrirá la norma ante los tribunales (opens in a new tab)
- grokipedia.comPower usage effectiveness (opens in a new tab)
- europapress.esSpainDC, la patronal de los centros de datos, recurrirá el real decreto y pedirá su suspensión cautelar (opens in a new tab)