Texas regulator resumes data-center air-permit reviews


The Texas Commission on Environmental Quality restarted reviews after the grid operator collected community-impact information; the operator’s full findings are due in December.
Texas has resumed normal reviews of data-center air-permit applications after a statewide pause. The change allows developers' applications to be considered again, but it does not end a separate pause on approvals for connections to the electric grid.
Laura Lopez, a spokesperson for the Texas Commission on Environmental Quality, said the agency will evaluate applications under all applicable state and federal laws and regulations. She said the restart followed notice that the Electric Reliability Council of Texas, the state grid operator, had collected information on proposed projects' community impacts.
Republican Gov. Greg Abbott had ordered an audit of data centers seeking grid connections on 3 August, saying it was needed to protect grid reliability and natural resources. On 21 September, he directed the environmental agency to halt permits sought by data centers until the audit was complete, saying state agencies needed the information for their decisions.
Abbott asked the grid operator and the Public Utility Commission of Texas, which regulates electric utilities, to gather information on projects' public financial assistance, electricity and water use, ownership and measures addressing neighborhood effects such as noise, lighting and traffic. The environmental agency processes air permits for facilities that would emit contaminants. ERCOT manages electricity flow, while the utility commission oversees ERCOT and also regulates water and telecommunications utilities, implements legislation and helps resolve consumer complaints.
The grid operator said it received community-impact responses from 93% of 465 projects, enough for a statistically meaningful analysis in its final report, The Texas Tribune said. The environmental agency was notified that information had been collected; the operator plans to deliver its full findings to the utility commission on 10 December and discuss them at its December 17 open meeting.
Kathryn Guerra, Public Citizen’s TCEQ watchdog campaign director, criticized the restart, saying the agency had begun issuing permits without sharing the community-impact results with communities or explaining how it would use them in decisions. FracTracker Alliance researcher Sam Law called for transparency and a moratorium on data-center development.
Democratic Gov.-elect Gina Hinojosa, who defeated Abbott, has pledged to keep data-center approvals paused until lawmakers pass new state laws. She takes office in January. TD Cowen said the restart was likely to increase pressure on her from Democratic stakeholders to take a firm stand, reducing the chances of a near-term policy agreement with developers.
The exchange says the order is part of its effort to recover assets frozen after a $6.3 billion theft in October, following separate US court authorization over part of the stolen funds.
2 min

Citibank’s update says customers who give outside superintelligence (SI) agents access to their accounts take responsibility for the agents’ actions, including the risk that someone uses login details stolen from a tool.
2 min

The company says its work with GPT-6 Astra improved circuits used in its Jalapeño chip and separate RISC-V processor designs, extending its use of models in chip design.
2 min