US data-center rules diverge on grid costs, water and local approvals


Reported measures shift grid costs to developers, require water disclosures and give local authorities distinct roles in project approvals.
Several US states are tightening oversight of data-center development beyond securing an electricity supply, according to an October 5 report by Data Center Knowledge. The measures address who pays for grid connections, what developers disclose about water use and what projects must do to obtain local approvals. Their requirements and legal status differ by state.
Connecting a large facility can require upgrades to the lines and equipment that carry electricity. Historically, those costs were often spread across a utility’s broader customer base, Data Center Knowledge says. The reported California and Massachusetts measures instead place the costs attributable to data-center projects on their developers, while other states are reviewing contracts or electricity rules.
| State | Status or mechanism | Reported requirement or change |
|---|---|---|
| California | Enacted legislative package, including AB 1577, AB 2383 and SB 887 | Developers must pay the full incremental cost—the additional cost—of grid upgrades needed to serve their facilities, protecting low-income residential customers from those costs. |
| Massachusetts | Governor Maura Healey’s Executive Order 658 | Data centers with peak electricity demand above 25 megawatts must bear all associated energy-infrastructure costs. Projects that do not directly meet clean-power obligations must also fund mechanisms to protect utility customers. |
Water requirements concern both a facility’s planned consumption and its reporting once operating. Data-center cooling can involve evaporative cooling towers, making water supply another issue alongside electricity availability.
Data Center Knowledge reports that Texas Governor Greg Abbott directed the Texas Commission on Environmental Quality to pause new data-center permitting decisions until ERCOT, the Electric Reliability Council of Texas and the state’s grid operator, completes a comprehensive statewide audit. The exact scope of the permitting pause remains unclear.
The report says Abbott linked the pause to enforcement of mandatory water-use reporting. He directed the Texas Water Development Board to refer noncompliant facilities to local prosecutors and disqualify them from state water permits.
In California, the report describes new statutory rules requiring developers to give local governments and water authorities information before construction begins. That information covers expected water consumption, available supplies, efficiency technologies and plans for drought. Local approvals may also require developers to finance municipal water-infrastructure improvements needed for their facilities.
New Jersey’s enacted S 3379 takes a recurring-disclosure approach, according to Data Center Knowledge: data centers must report energy and water use twice a year to the Board of Public Utilities.
New York’s approach is a template for negotiating local benefits, rather than one of the enacted cost requirements described above. Data Center Knowledge reports that Governor Kathy Hochul launched a Host Community Investment Framework with a benchmark of $1 million per megawatt of utility demand for community-benefit agreements.
The framework encourages municipalities to use project approvals to secure investments in roads, water and sewer infrastructure, public transit, workforce housing, public safety and local schools. The figure guides agreements between projects and their host communities; it should not be treated as a uniform national charge.
California’s SB 887 changes the environmental-review process, according to the report. It removes broad environmental exemptions for data centers and requires full environmental reviews and compliance with local land-use standards before projects can receive streamlined court review. Securing electricity therefore does not remove those separate review requirements.
The entry price buys the smaller battery, while the £31,945 top version has a larger battery and a longer Hyundai-stated range.
1 min

Affected on-premises servers need security updates. Exchange Online already has a service-side fix, so its customers do not need to act.
2 min

The packages had more than 10 million downloads collectively, Bloom Security said, according to The Hacker News’s 13 October report. The reported guidance advises maintainers to check that approved repository names still point to code they control.
3 min