Software issue shortens BepiColombo’s Mercury burn, ESA says


The European Space Agency says the spacecraft entered orbit safely on 21 November and its teams are investigating what happened. An update is expected on 23 November.
Situation: BepiColombo's Mercury orbit insertion
A software issue shortened BepiColombo’s thruster burn during its insertion into Mercury orbit, the European Space Agency (ESA) said on 22 November. The agency confirmed that the spacecraft had successfully entered orbit and said it was safe. Teams at the European Space Operations Centre are working to understand what happened, CNA said.
Mercury’s gravity had already caught the spacecraft in a long orbit. The burn was meant to tighten that orbit, with four thrusters on ESA’s Mercury Planetary Orbiter scheduled to fire for 37 minutes.
Earlier: BepiColombo’s connected spacecraft enter Mercury orbit
BepiColombo is a joint mission of ESA and the Japan Aerospace Exploration Agency (JAXA). ESA’s Mercury Planetary Orbiter remains attached to JAXA’s , known as Mio. The European orbiter is designed to study Mercury’s surface, interior and thin outer atmosphere; Mio will study its magnetic field and magnetosphere, the region shaped by that field.
BepiColombo launched on 20 October 2018 and used nine planetary flybys to shed speed: one of Earth, two of Venus and six of Mercury. NASA’s Mariner 10 was the first spacecraft to visit Mercury; its MESSENGER was the first to orbit the planet, from 2011 to 2015.
A separate propulsion problem in 2024 reduced the power of the Mercury Transfer Module’s electric thrusters. The mission changed course, delaying its planned arrival from December 2025 to November 2026. The transfer module, which carried the orbiters, separated on 3 September 2026, leaving the European orbiter’s thrusters to steer them.
Before the software issue was disclosed, ESA’s plan called for five burns to shrink the orbit ahead of Mio’s release. The agency’s July timeline listed the following steps, while cautioning that dates could change for operational reasons:
ESA said it would provide an update on 23 November.
The European and Japanese orbiters are scheduled to separate on 9–10 December and enter individual polar orbits, with science operations planned for April 2027.