Grid approval puts Oracle’s Wisconsin 2027 target at risk, Aterio warns


The grid-connection approval process restarted in September. Even after first power arrives, the campus’s electrical and cooling systems must be tested before they can support customers.
Oracle’s Project Lighthouse datacenter in Wisconsin could miss its target of delivering capacity to customers in the second half of 2027 because the grid connection still awaits regulatory approval. Research company Aterio warned of that risk in an October 2 report by The Register.
Vantage is developing the campus in Port Washington, with Oracle as tenant. The Register reports that the campus is rated for 902 megawatts of computing load and 1.3 gigawatts—1,300 megawatts—of total electricity demand.
American Transmission Company (ATC) needs permission from the Public Service Commission of Wisconsin (PSC), the state regulator, to build the campus’s grid connection. According to The Register, the commission closed the original case after withdrawing its finding that ATC’s application was complete. ATC refiled in September 2026, restarting the approval process.
That approval must come before transmission construction can begin. Aterio says the campus cannot operate until ATC connects it to the grid, so the regulatory process affects when Oracle can make the capacity available to customers.
Analysis
Aterio projects different power-delivery dates depending on how long approval takes. These are the research company’s scenarios, not an approved regulatory timetable or a confirmed change to Oracle’s delivery target.

| Scenario | Partial power | Full power supply |
|---|---|---|
| Earliest, considered highly unlikely by Aterio | October 2027 | August 2028 |
| Base case | December 2027 | October 2028 |
| Extended regulatory review | June 2028 | April 2029 |
Partial power in December 2027 would leave little time before Oracle’s target expires. Aterio explains that each building’s electrical and cooling systems must be energized, tested and commissioned—checked and prepared for operation—before they can support customers’ computing workloads. It therefore expects the campus’s electricity load to increase mainly from the first quarter of 2028.
The date of PSC approval remains uncertain, as does Oracle’s response to the Wisconsin timing concerns.
The CEO's aggressive target is for a prototype, not volume production, qualifying the earlier 2027-shipment plan. Volantis also targets about 20 kW of system power.
2 min

The company plans to use its $97 million Series B for volume shipments and development toward data-center-class performance.
2 min

The 22 images let researchers inspect previously unread code, but they do not amount to a working console unlock.
3 min
Correction ·
Corrected spelling and punctuation in the Armenian text.
Correction ·
In the Armenian text, thousands in numbers were separated by commas, which in Armenian mark decimals. They are now separated by spaces.